Haiti - News : Zapping...

Maritime Domain : Haiti deposits instruments of accession to ten international conventions

Haiti - Environment : A large delegation from Haiti is participating in COP31 in Turkey

Haiti - 2026-2027 D1 Opening Series : All results from the 1st matchday

Haiti - News : Zapping...


more news


Haiti appointed to the Vice-Presidency of the Standing Committee of the International Solar Alliance

Elections : The CEP discusses budget adjustments with the Haiti's Ministry of the Economy

iciHaiti - Mexicao : Haitian Ambassador visit's to the Huehuetoca military base

London : Discussion on the Haiti dossier with Chancellor Forbin

iciHaiti - D1 Championship : Opening Series begins (Day 1 schedule)


more news


Jacmel : Monitoring of the 4 MW solar power plant construction project


Jacmel : Monitoring of the 4 MW solar power plant construction project

An information session followed by a site visit was held in Jacmel regarding the city's electrification project, specifically the construction of a 4 MW photovoltaic power plant in Mon-Fleurit. https://www.haitilibre.com/en/news-46650-haiti-technology-construction-of-a-major-solar-power-plant-in-jacmel.html

During the meeting, the project coordinator noted that the initiative had been in development since 2019 and subsequently received US$7 million in funding from the World Bank https://www.haitilibre.com/en/news-46649-haiti-news-zapping.html through the SREP program. Overall coordination is being provided by the Ministry of Public Works. The project is being carried out by the Dominican international firm ESD Engineering Service S.R.L. The project is currently scheduled to be commissioned in March 2027.

The mission also aimed to strengthen the project's monitoring and information system. Plans include establishing two coordination offices, one at the existing thermal power plant and the other at the future Mon-Fleurit photovoltaic site. These offices will facilitate access to information for institutions, citizens, and other stakeholders.

Securing the site is also among the next steps, with the construction of fences to protect the facilities and the area designated for the solar panels and other equipment.

Finally, the meeting emphasized the need to strengthen the involvement of local stakeholders. A future mission is expected to reconstitute the project's monitoring committee, with increased participation from the Jacmel City Hall.

With a projected capacity of 4 MW and an estimated lifespan of approximately 20 years, this project represents a significant initiative for the development of solar energy production and the strengthening of Jacmel's electrical grid.

See also :

https://www.haitilibre.com/en/news-46650-haiti-technology-construction-of-a-major-solar-power-plant-in-jacmel.html

https://www.haitilibre.com/en/news-46649-haiti-news-zapping.html

IH/ iciHaiti



Twitter Facebook Rss Add to favorites
Send news to... Daily news...




Why IciHaiti ? | Contact us | Français
Copyright © 2010 - 2026
IciHaiti.com